4 Lenz: Flow Metrics Widgets

Features and Functionality

Important: This feature is currently in BETA and will need to be enabled for your company prior to use. A Company Admin can contact their Customer Success Manager to set this up. In order to pull data from your ALM into this dashboard, you will need to set up Integrations first. 

This article is part of our series on the Features and Functionality of the 4 Lenz Dashboard. We've broken each area down for you, into shorter articles.

Screenshot 2023-12-18 at 12.11.46 PM.png


Predictability

Sprint Level Predictability displays the percent of committed work items that were completed across the completed sprints for the last 90 days. This widget works for teams pulling in data from Jira Scrum boards (not Kanban boards).

When data has been entered manually for a team, the numbers entered for Committed Points and Completed Points for each sprint that ended in the last 90 days are considered and then averaged to obtain the displayed value.

Variance is shown next to the percentage in the widget in green when there is an increase and in red when there is a decrease. Variance is determined at the individual team level by the following formula: (new value - old value / old value). Variance % is determined for the multi-team level and above by aggregating the percentages for each individual team and dividing by the number of teams to get an average.

Screenshot 2023-10-10 at 5.10.04 PM.png

Click the three-dot icon to select the Predictability Formula link and see the formula behind the widget when data is populated via an integration.

Screenshot 2023-10-10 at 6.04.55 PM.png


Throughput

This widget displays both Feature and Story-level Throughput. Change the view using the down arrow in the widget.

Feature Throughput

Feature Throughput displays the number of features that were completed by the team in the last 90 days.

When data is entered manually for a team, the numbers entered for Actual Throughput for each sprint that ended in the last 90 days are considered and then averaged to obtain the displayed value.

Variance is shown next to the percentage in the widget in green when there is an increase and in red when there is a decrease. Variance is determined at the individual team level by the following formula: (new value - old value / old value). Variance % is determined for the multi-team level and above by aggregating the percentages for each individual team and dividing by the number of teams to get an average.

Screenshot 2023-10-10 at 5.10.11 PM.png

Click the three-dot icon to select the Throughput Formula link and see the formula behind the widget when data is populated via an integration.

Screenshot 2023-10-10 at 6.05.16 PM.png

Story Throughput

Story Throughput displays the number of stories that were completed by the team in the last 90 days.

When data is entered manually for a team, the numbers entered for Completed Stories for each sprint that ended in the last 90 days are considered and then averaged to obtain the displayed value.

Variance is shown next to the percentage in the widget in green when there is an increase and in red when there is a decrease. Variance is determined at the individual team level by the following formula: (new value - old value / old value). Variance % is determined for the multi-team level and above by aggregating the percentages for each individual team and dividing by the number of teams to get an average.

Screenshot 2023-10-10 at 5.10.20 PM.png

Click the three-dot icon to select the Throughput Formula link and see the formula behind the widget when data is populated via an integration.

Screenshot 2023-10-10 at 6.21.41 PM.png


Velocity Delta

Velocity Delta shows by what percent the velocity has improved or declined in the last 90 days. This widget works for teams pulling in data from Jira Scrum boards (not Kanban boards).

When data is entered manually for a team, the numbers entered for Completed Points for each sprint that ended in the last 90 days are averaged and then compared to the average of the numbers entered for Completed Points for each sprint that ended in the last 91-180 days to find the percentage increase or decrease.

Screenshot 2023-10-10 at 5.10.28 PM.png

Click the three-dot icon to select the Velocity Delta Formula link and see the formula behind the widget when data is populated via an integration.

Screenshot 2023-10-10 at 6.05.29 PM.png


ROI Efficiency Gained / Avg Story Cycle Time

ROI Efficiency Gained

ROI Efficiency only displays at the multi-team level and above. At the individual team level, this widget displays story cycle time.

ROI Efficiency Gain displays the dollar efficiency gained or lost during the last 90 days. This is determined by the feature throughput variance. ROI Efficiency is improved as the feature throughput increases and declines as the feature throughput decreases.

ROI Efficiency at multi-team and above levels is determined by aggregating the ROI Efficiency from all individual teams and is the same calculation for data from an integration and manually entered data.

Screenshot 2023-10-10 at 5.13.21 PM.png

Click the three-dot icon to select the ROI Efficiency Gain Formula link and see the formula behind the widget.

Screenshot 2023-10-10 at 6.16.18 PM.png

Average Story Cycle Time

The Avg Story Cycle Time widget is available only at the team level. This widget measures how long it took on average to complete stories over the last 90 days.

When data is entered manually for a team, the number of days entered in the Story Cycle Time field for each sprint that ended in the last 90 days are considered and then averaged to obtain the displayed value.

Variance is shown next to the percentage in the widget in green when there is an increase and in red when there is a decrease. Variance is determined at the individual team level by the following formula: (new value - old value / old value). Variance % is determined for the multi-team level and above by aggregating the percentages for each individual team and dividing by the number of teams to get an average.

Screenshot 2023-10-10 at 5.10.37 PM.png

Click the three-dot icon to select the Avg Story Cycle Time Formula link and see the formula behind the widget when data is populated via an integration.

Screenshot 2023-10-10 at 6.05.42 PM.png


Story Points Delivered

Screenshot 2023-12-18 at 12.11.09 PM.png

This widget displays a timeline of the team's sprints for their selected PI or quarter. The widget displays all the sprints for the selected quarter or Planning Increment and shows target vs actual story points delivered. The quarter is noted next to the widget title. This widget works for teams pulling in data from Jira Scrum boards (not Kanban boards).

When data is entered manually for a team, the numbers entered for Target Points and Actual Points for each sprint are considered and then plotted based on the ‘To’ date of the sprint, which is the end date.

Use the scroll bar to see the data for each Sprint. Change quarters by clicking on the arrows to the left and right of the chart or the dots at the bottom. No data will be displayed for quarters that do not meet the criteria for the widget.